CeTeau completed soil improvement for the Dhaka Mass Rapid Transit Development project in Bangladesh. The works were part of the Dhaka Metro Rail Line-6, which will provide a 20 km Metro Rail system for Dhaka, the capital of Bangladesh, which is one of the most highly populated and traffic congested cities in the world. The project will reduce traffic congestion and improve air pollution in the Dhaka City and thereby contributing to regional economic development and improvement of urban environment.

Project Data

Location : Dakha
Product : Vertical Wick Drain, CT-D1010
Country : Bangladesh
Quantity : 1,000,000
Client : Tokyu Construction Co. Ltd.
Period : Feb 2017 - March 2017